Are these times independent or should GR Processing Time INCLUDE the Average Inspection Duration.

 

If my AID is equal to 22 days for a inspection type, should the GR processing time include that value plus?


Comments

  • 02 Apr 2009 5:13 am Guest
    good points received
  • 13 Aug 2009 4:02 pm Guest
    Were you able to determine if you should include inspection duration in the GR processing time?
  • 31 Aug 2010 9:41 pm Guest
    GR Processing Time should include the AID time.
    Be advised that depending on the inspection types, these can differ.

    GR PT is ustilized during the plan phase of procurement or processing.