Change of date of planned orders between R/3 and APO

|| || 0

Change of date of planned orders between R/3 and APO
Stechies

Changing a planning order in R/3 causes dates to be changed in APO even if no date-relevant fields have been changed.
In the case of orders with consecutive accesses, incorrect receipt due dates are transferred to R/3. Instead of the access finish the start of the access is transferred.

The order deadline in APO differs from the availability date of the material produced, for example, because the goods receipt processing time, teardown time, wait time, or queue times are being used.