Hello,
I tried to close a project # 2600000089. I am getting an error message " There is still WIP for WBS 2600000089 ".
The long text suggests that " Calculate the WIP for WBS 2600000089 so that it can be cleared. Then settle WBS 2600000089, including the cleared WIP in the settlement ".
I am not clear with this information. What should I do for this ??
We went from 3.1H to 3.1I about 20 days back. In 3.1H I have never come across like this..
Thank you ..
- You have costs on the WBS that need to be settled to a cost center or other WBS
- You have RA that still needs to be run and settled
This can get comlicated if you are not doing full settlement as you will have to open up the past periods to fix it.