Hello All,

I want to display all my PM's (Preventative maintenance items) by their cycle time (frequency) rather than by their maintenance strategy - how can this be done?

Thanks in advance.


Comments

  • 14 May 2009 5:44 pm Guest Helpful Answer
    Query (sq01) can be created,
    Join conditions
    Table Table
    EAPL PLWP
    EQUI EAPL
    EQUI EQKT
    EQUI MPOS
    MPOS ILOA
    PLWP T351X

    => Maintenance package number PLWP-PAKET
    => Text for maintenance package/cycle T351X-KTEX1

    dxhelinski@saintfrancis.com
  • 18 May 2009 12:02 pm Roshan Helpful Answer
    Dear
    dxhelinski@saintfrancis.com

    need PM orders thru maint,stretegy with due packeges
    1-first week of the month
    1 2-sec.week
    1 2 3-third week
    1 2 3 4-forth week.

    pl guidde.


    regards
    roshan
  • 18 May 2009 7:37 pm Guest Helpful Answer
    Not sure if this is what your looking for, but I use tranaction code
    IP16 - Maintenance Plans List Editing Display - I run this report to give me a listing of all PM plans created and it give me the following informaiton with cycle start dates. Then you can adjust the report to include the scheduling period(frequency) and scheduling intervals attached below is an example.

    Maint Plan start of callno. Scheduling Scheduling
    cycle Period Interval
    GBP-605-SUMP 03/01/2007 12 80 30 DAYS

    Hope this helps.

    rhonda.miller@merisol.com
  • 14 Dec 2010 5:47 am Guest
    I want to see PM Cycle ( From Notification to complition )

×