Hi Friends,
We have a business requirement in which during execution of cable laying services in field increased due to deviation(hard Rock). Therefore to get the extra budget we need to increase the planning / Revise the planning..
During revision of planning in PS , it was found that Purchase Requisition which was generated from projects (cj20n) is under non editable mode due to this we are not able to update the plan in Projects.
We have tried to change the PR through converting the Message No. SE-721 from Error to Warning. It worked but others PR's(used by other module) are also under editable mode and there is no check on the PO open quantity with PR).
please suggest any workaround for the same.
Thanks