Hello Experts,
How to re-import delivery units that failed during SAP HANA upgrade, here are two possibilities exist first one is you can re-import the failed delivery units via Modeler perspective and the second one is If many delivery units failed during upgrade you could just update the repository using the utility 'hdbupdrep'.
Here are two possibilities exist.
You can re-import the failed delivery units via Modeler perspective [Modeler Perspective-->Quick View --> Import -->SAP HANA Content --> Delivery Unit --> Select System for re-import --> Select "Server" --> Select "Delivery Unit" --> Select Actions "Overwrite inactive objects" and "Activate Objects"]
Alternatively if many delivery units failed during upgrade you could just update the repository using the utility "hdbupdrep", you can find the utility on the OS under the path
/usr/sap/<SID>/SYS/global/hdb/install/bin>
Once the repository is updated log will be written under /var/tmp directory and will have the following naming convention.
/var/tmp/hdb_<SID>_UpdateRepository_<timestamp>/hdbupdrep.log