Pre-requisite: Level 1 WBS Element = Project Controller Level 2 WBS Element = Plant/Unit Controller Client need that After released and approved the date for Plant/units from plant controller & Project controller, plant controller should be restricted from updating/changing any approved information like the date of plant/units level and only project controller should have this authority.
Thanks in Advance.
You can view more tutorials about SAP PS
Dear All for better understand,
Is there any standard way or enhancement available to control authorization
for users with certain status for WBS Element i.e. for example
Pre-requisite:
There is only 2 level of project i.e.
Lev_ WBSE_______Description
1___ 7-14.E_______summary outage controller
2___ 7-14.E.2310__ Plant/unit # 2310
2___ 7-14.E.2310__ Plant/unit # 2220
Project Controller (authorization role assigned "Z_PS_OP7_OTGCON_C") have
all project level authorization
Plant/Unit Controller (authorization role assigned
"Z_PS_OP7_PLNTOTG_C_2310") have only level 2 authorization with enhancement
that we did in system by Z table.
User ID_ Plant #
123345_ 2310
122455_ 2220
Issue:
After System Status released and User Status approved the WBS basic date
for Plant/Units should be restricted from updating/changing by Plant/Unit
Controller level and only project controller should have this authority.
Solution required:
Can anyone tell how to control this scenario either by standard or
enhancement available to control authorization?