PO Net Price 0

Updated May 19, 2018

When I am trying to create PO via me59, I get the error that PO shouldn't have net price as 0. In info record, the price is zero. But, in that case shouldn't the net price should be selected from last created PO ? Which it is not selecting. Please advice.
 
Thanks in Advance.


Comments

  • 16 Oct 2013 9:52 am Sushma
    I also faced the similar issue; as in this case prices will be pulled up
    from info record. At last we created PO's by providing the PR's from the
    Document overview of ME21N for zero price materials.
  • 16 Oct 2013 9:53 am Sushma
    what is the material price in the purchase requisition? what is the price
    in the material master? is there a contract in place?

    the adoption of the info records price is dependent on whether the info
    update indicator checkbox was selected when the last PO was created.

    if an info records exists for a material/vendor combination, the price is
    adopted from the info record.

    if no info record exists then the price from the material master is
    adopted in the PO.

    if you have set up the functional auth for PO's in cofig and have selected
    the adopt PO price checkbox, then the price from the PR is adopted into the
    PO.

    if you have a contract set up and a source list, then the price from the
    contract is adopted on the PO

    supply more info to assist.
  • 10 Dec 2013 1:09 pm Nanda Kumar
    Try to maintain PIR with some price other than zero.
    (Price pick up will have priority from Inforecord first)

×