Hi ALL,

recently i face a Q in interview about transport he want to know that is their any way through we can reverse the transport means to say can we move the request from PRD to QAC to DEV i know we can do it through TP command but he want to know can we do it with SAP GUI.

I don’t want to delete the old route ie DEV to QAC to PRD without deleting this old Route i want to create new Reverse route

is this possible if yes then please advice how

Thanks in advance

Bye
Manoj


Comments

  • 08 Apr 2008 7:35 am Guest
    It can not be possible.
  • 05 May 2008 12:08 pm Guest
    It's Impossible to reverse the Transports.
    i.e. PRD ---> QAS ---> DEV
    Transport route is Unidirectional.

    Warm Regards
    Ramesh Chegondi
  • 25 Jul 2008 7:34 am Sandeep Pawar
    Why it is not possible...?
    cant we define the reverse transport route....
  • 12 Aug 2008 9:23 am Guest
    Hi,

    I think we can do transport from PRD to DEV as I successfully created a transport route from PRD to DEV.

    Shivam Mittal
  • 17 Aug 2008 12:42 pm Guest
    Hi

    This can be done by using transport of Copies.


  • 26 Aug 2008 4:06 pm Guest
    Hi,
    It is not possible to reverse the reqeusts which has got imported into PRD , the Transports routes

    are confiugred to be in one direction only DEV->QA->PRD . However there are third party tools like

    Transport express which achieve this reversal. you can take a look . Not sure whether SAP supports it .

    Rgds
    Kumar
  • 27 Aug 2008 7:21 am Guest
    Hi,

    Transport routes are unidirectional, so we cant reverse the request in other way. There are some third party tools available through which you can achieve this. These are not SAP certified tools however.

    Regards,
    Goyal
  • 22 Sep 2008 6:53 pm Guest
    Hello There,

    As it is mentioned by all other Guru's it is not possible to reverse the transport, it is always an unidirectional flow of information. Because when you configure the TMS you have assign the source and target system. Unless you clear the old system and reconfigure your TMS using your consolidation route from PRD to QAS and Delivery route from QAS to DEV. but it is not the way the sap works. it was a trick question to find out whether you have really worked on the system before or not.

    Good luck,

    Jayesh

×