One can match ChaRM scenario with 2 SAP Landscapes along with one DEV system. And one can do it with the following scenario:
1.One DEV System which will be called as DEV (1)
2.Two Q&A System which will be denoted as Q&A (1) and Q&A (2)
3.Two Pre-PROD systems will be denoted as P-PRD(1) and P-PRD(2)
4.Two PROD systems will be denoted as PRD(1) and PRD(2)
5.One ChaRM Project
2 Landscapes which will be assigned to that one ChaRM Project will look like that:
1. DEV(1) -> Q&A(1) -> P-PRD(1) -> PRD(1)
2. DEV(1) -> Q&A(2) -> P-PRD(2) -> PRD(2)
Following the above given scenario one want to Create Urgent Change and move TRs ONLY to PRD(1) : DEV(1) -> Q&A(1) -> P-PRD(1) -> PRD(1) and then move TRs which are already in PRD(1) to PRD (2) : DEV(1) -> Q&A(2) -> P-PRD(2) -> PRD(2) using the same.
For these changes one need to follow the following steps:
If one need to Create Urgent Change and move TRs ONLY to PRD(1) : DEV(1) -> Q&A(1) -> P-PRD(1) -> PRD(1) -> is only possible just by selecting the iBase of prod1 system and it's transported to this track only. After that he need to move TRs which are already in PRD(1) to PRD (2) : DEV(1) -> Q&A(2) -> P-PRD(2) -> PRD(2) using !!!the same!!! Urgent Change -> Possible with report Report /TMWFLOW/SCMA_BTCH_SYNC_TEST.