The "Setup Early Watch Alert for SAP Solution Manager 4.0" tutorial.

After completing the session you will know how to prepare your SAP Solution Manager system and the connected systems for the processing of Early Watch Alerts.
Setup Early Watch Alert for SAP Solution Manager 4.0.

The SAP tutorial will show how to set up an early Watch Alert for a system which is connected to the SAP Solution Manager.
 



Sap Early Watch Alert: Benefits
 



You can fined an overview presentation about Early Watch Alerts (EWAs) on Sap Service Marketplace at http://service.sap.com/rkt-solman.
The presentation gives more details on the benefits of early Watch Alerts.
 



SAP Early Access Customer Relationship Management
First, the system for which Early Watch Alerts (EWAs) should be generated needs to be connected to the SAP Solution Manager. This can be done and checked in transaction SMSY.





System Landscape
Create a new system in transaction SMSY. The relevant steps are explained in other SAP Tutors.
 


Which you can find via SAP Service Marketplace via http://service.sap.com/rkt-solman.
Please see "System Landscape (SMSY) – creating Systems" and "System Landscape (SMSY) –Creating RFC Connections" for more details.
 



System CTA, Main Instance R/3 Server Change

In this example, an ECC 5.0 system named "TCE" has been registered and connected to the Solution Manager system via transaction SMSY. In the next steps, this system has to be assigned to a logical component.
 



Again, this is described by another SAP Tutor available on SAP Service Marketplace at http://service.sap.com/rkt-solman.
 



Logical Component Z_CTA Change
The system TCE was assigned as a Development system to the newly created Logical component "Z_SAPTUTOR_ECC".
 



Logical Component Z_CTA Change

For setting up the solution, transaction DSWP (or "SOLUTION_MANAGER") is used.

 


SAP Solution Manager: Active Solutions
Currently, only one solution named "SAP Tutor Solution" exists.

 


For the creation of a solution and its settings, there are also SAP Tutors on SAP Service Marketplace at http://service.sap.com/rkt-solman.

 


Change Solution Directory
The logical component Z_SAPTOR_ECC is assigned to the "SAP Tutor Solution".
 



Change Solution Directory
In the solution settings, Monday is specified as the processing day for Early Watch Alerts (EWAs), and the TCE system is tagged for producing Early Watch Alerts (EWAs).
 



SAP Solution Manager: Active Solutions
By including the system TCE in the EWA solution settings, a new EWA session has been automatically created for this system. You can check this by displaying the EWA session overview of the "SAP Tutor Solution". Click on "SAP Tutor Solution".





SAP Solution Manager: SAP Tutor Solution
Click on "Operations".
 



SAP Solution Manager: SAP Tutor Solution
Click on "Solution Monitoring".
 



SAP Solution Manager: SAP Tutor Solution
Click on "Early Watch Alerts".

 


SAP Solution Manager: SAP Tutor Solution
You can access detailed session information by clicking on the session. The red flag means that this session is overdue – the solution Manager waits for the connected system to deliver the session data. Click on "SAP Early Watch Alert".
 



SAP Solution Manager: SAP Tutor Solution
You see details for this specific EWA session. Sometimes, it is quite helpful to look for the session number (you can see this session number also in the connected system).
 

 


SAP Solution Manager: Due date exceeded
Now, the4 new Service Data Control Center (SDCCN) has to be configuration. This can be done using the SAP Solution Manager Implementation Guide (IMG). Call the SAP Solution Manager IMG via transaction SPRO. Type in "/nspro" and press Enter.





Customizing: Execute Project
Access the SAP Reference IMG by clicking on the relevant button.

 




Display IMG
Expand "SAP Solution Manager".
 



Display IMG
Expand "Basic Settings".




Display IMG
Expand "SAP Solution Manager System".
 



Display IMG
Expand "Operations".
 



Display IMG

Expand "Setup Service Data Control Center".

 

 




Display IMG
In the first step towards the setup of SDCCN, includes need to be generated. Execute "Generate Includes for service Data Center".
 



SAP
Configuration the generation of the reimport includes by clicking "Yes".
 



SAP
The includes are generated. This can take several minutes. Scroll down to see a stop watch and the message "Compiling" at the bottom of the GUI screen.
 



Generating reimport includes
If everything went fine, you receive an output list of the includes that have been generated ("Generation of was successful".).
 



Generating reimport includes
Click on the "Back" button to go back the Solution Manager IMG.
 



Display IG
The SDCCN of the Solution Manager and the satellite systems can be configured. This can be done via the SDCCN Administration which can be accessed via transaction SMSY. Execute "Activate the Service Data Controle Center centrally in the Solution Manager". This will take you to transaction SMSY.
 



System Landscape
To access the SDCCN Administration for transaction SMSY, click on "Goto".

 

 




System Landscape
Click on "Solution Manager Operations".

 

 




System Landscape
Choose "Administration SDCCN" from the menu.
 



SAP
This will show the SDCCN Administration window. The SDCCN of your Solution Manager system should already be activated, and the Solution Manager should be defined as the master system of your landscape.
 



The SDCCN is explained in various SAP Tutors which you can access on SAP Service Marketplace via http://service.sap.com/rkt-solman
 



SAP
To access the Solution Manager SDCCN, click on "Execute". You can also access the SDCCN via transaction SDCCN.


Service Data Control Center
You see the (local) SDCCN tasks of the Solution Manager. To ensure that the Solution Manager itself is also able to deliver EWA session data, check the relevant RFCs. Click on "Goto".
 



Service Data Control Center
Choose "Settings"- "Task-specific" from the drop down menu.
 



Settings –Task-specific
Access "Settings" underneath "RFC Destinations" from the "Tasks-specific settings" tree by clicking on the relevant icon.
 



Settings –Task-specific
On the "Destinations" tab, you should always see at least two destination: the destination SDCC_OSS is a copy of RFC destination SAPOSS and leads to SAP. It is used for refreshing service definitions. The other destination is called "Back" destination and leads to the Solution Manager system. This destination is used to transmit EA session data. As the overview shows, the RFC destinations for the Solution Manager itself, the Back destination, leads to the same system ("NONE").
 



Settings –Task-specific
Click on "Cancel" to leave the RFC destination overview.
 



Settings –Task-specific
Click on "Back" to leave the SDCCN Task-specific settings.

 

 




SERVICE Data Control Center
Click on "Back" to leave the Solution Manager SDCCN.
 



SAP
Now the SDCCN of the system TCE needs to be activated. The system TCE therefore needs to be added to the SDCCN Administration list. Click on the "Add system" button.
 



Expand "SAP ECC".
 



Expand "CTA".
 



Choose client "000". This is the client to which RFC destinations have been maintained.
 



Scroll down and confirm your selection by clicking "Continue".

 



SAP R/3
If you have not specified a trusted system RC destination, you might be requested to log on to the newly connected system TCE. This will allow the Solution Manager system to check the status of the remote (TCE) SDCCN.







SAP
System TCE has been added to the SDCCN Administration list. However, the SDCCN status of the system is probably not green. Click on the yellow warning icon to get more details.

 




SAP
Obviously, the SDCCN in system TCE is not active yet. Confirm the information by click "Continue".
 



SAP
To activate the SDCCN of system TCE remotely, click on the relevant icon in column "Call SDCCN".





SAP
The activation of the SDCCN in the remote system TCE includes the automatic generation of RFC destination SDCC_OSS which lead to the SAP Service system (OSS). It is recommended to have this RFC. It is recommended to have this RFC destination generated.
Confirm the generation of the RFC destination by clicking on "Yes".
 



SAP
The SDCCN of system TCE has been activated remotely- check for the "green" status of TCE SDCCN. This was possible because the system re-used the credentials (logon+ password) which were provided when adding the system TCE to the SDCCN administration. Now the SDCCN of system TCE can be directly accessed. Click on the Execute icon to access the SDCCN of system TCE.
 



Service Data Control Center
This takes you to system TCE. You see the task overview within the SDCCN of system TCE. During the (remote) activation of the SDCCN, two new tasks have been created. The "Maintenance Package" task guarantees that the EWA sessions that have been defined in the Solution Manager for system TCE are carried out. When this "Maintenance Package" task runs next time, it will (beside other actions) access the Solution Manager and look if any EWA session have been scheduled. These session would show up as new tasks in the SDCCN.
For the task handling of the SDCCN, SAP Tutors exist on SAP Service Marketplace. They can be accessed via http://service.sap.com/rkt-solman.
However, for this tutorial, the EWA sessions scheduled for system TCE can be fetched manually. A new task needs to be created for this.





Service Data Control Center
To create a new task, click on "Task" in the menu bar.
 



Service Data Control Center
Choose "Create" from the menu.
 



Service Data Control Center

Select "Refresh sessions" from the list.
 



Service Data Control Center
Confirm your selection by clicking on "OK".
 



Service Data Control Center
You need to configure the newly create task = e.g. how often and when it should be executed. Change the execution time to "Now".
 



Service Data Control Center
Check that the task runs only once: "Runs once" should be displayed in the Task –specific settings. Scroll down and click on "Continue" to confirm your settings.
 

Service Data Control Center
The task is created Click on "Continue".
 

Service Data Control Center
The "Refresh sessions" task is created and immediately started (see the "Activation" icon in the status column of the tasks).
Click "Refresh" to see the current state of the running task.


 



Service Data Control Center
The status icon of the task will switch to the "Generation" icon after some time.
 



Service Data Control Center

Click on the "Refresh" button again.
 



Service Data Control Center

After some time (can take up to several minutes), the "Refresh sessions" task has finished (and disappears from the "To do" list of SDCCN- you can see it in the "Done" list). this time, the "Refresh sessions" task has found several EWA sessions which have been scheduled for system TCE. These are now newly listed as tasks in the "To do" list of SDCCN.





Service Data Control Center
Usually, these "Early Watch Alert for Solution Manager" tasks are automatically carried out in the system by the task processor. You can check if the task processor is running correctly: Click on "Goto" in the menu bar.





Service Data Control Center
Select "Settings" – "Task processor" from the menu.
 



Service Data Control Center
You should see that the task processor job is activate. You can also see when it is scheduled to run next time.





Service Data Control Center
Click on "Continue".

 

 




Service Data Control Center
For this tutorial, one EWA task will be started manually. Select the row with the first EWA task.
 



Service Data Control Center

Click on "Edit" in the menu bar.
 


Service Data Control Center
Select "Start now" from the Edit menu.




Service Data Control Center
Confirm the start of the task by selecting "Yes".
 



Service Data Control Center
The EWA task has been started. The status icon has changed to "Activation" icon. Click on "Refresh".
 



Service Data Control Center
After some time, the status icon will change to the "Generation" icon (can task serval minutes).

 




Service Data Control Center
Click again on "Refresh".




Service Data Control Center

More details on the processing of the EWA task can be seen in the log. Double click on the "Log" icon.

 



Log: ID "0000000321' –Request session data

You see the detailed steps that are processed by the EWA task – mainly the collection of data from the system components.
 



Log: ID "0000000321' –Request session data
Click "Back" to go back to SDCCN task overview.
 



Service Data Control Center
Click the "Refresh" button again.
 



Service Data Control Center
After some time (can take up to 30 minutes), the EWA data has been collected and transferred to the Solution Manager system. The EWA task is finished and disappears from the "TO do" list of the SDCCN.
 



Service Data Control Center

You can check the finished EWA task in the "Done" list of SDCCN. Click on the "Done" tab.
 



Service Data Control Center

You can still access the log for the EWA task. You can also check if the data has been transmitted correctly to the Solution Manager. Double click the "Transportation" icon.
 



Session Data Viewer
You can expand the tree to the details on the various components. Click on the "+" sign.
 



Session Data Viewer
To live the transport details, click on "Back".
 



Service Data Control Center

Now data for EWA session has been collected and transported. The SDCCN of the system TCE can be left to check if the EWA data has successfully arrived in Solution Manager.
Click on "Back" to leave the TCE SDCCN and go back to SDCCN Administration of the Solution Manager.





SAP


Back in the SDCCN Administration of the Solution Manager, we can leave the window. Click on "Continue".

 

 



System Landscape

To check the EWA session data from the system TCE, transaction DSWP (or SOLUTION_MANAGER") needs to be called. Enter "/ndswp" then press Enter.





SAP Solution Manager: Active Solution

From the Active Solutions overview, you can directly access the EWA reports of a Solution. Click on the icon for the Early Watch Alert Reports of the "SAP Tutor Solution".
 



SAP Solution Manager: Active Solution

In the overview for the EWA reports of the "SAP Tutor Solution", you see the various EWA sessions scheduled for system TCE (this is currently the only system within the solution). Notice the different icons beside the EWA sessions – there is one which is ready for processing (the one that data has already been transferred from system TCE), one which is overdue (red flag), and one scheduled for some time in the future (to be precisely: upcoming Monday, as Monday was specified to be the processing day for this solution).





SAP Solution Manager: Active Solution

Click on the EWA session with the two tiny test tubes beside it.







SAP Solution Manager: Data is available

All necessary data for this EWA session has been transferred from system TCE. The session data now needs to be processed in the Solution Manager. This is usually done on a regular basis by the "SM:EXEC SERVICES" background job in solution Manager.
 



SAP Solution Manager: Data is available

For this tutorial, the service processing can also be starting manually. Click on "Start service processing".





SAP Solution Manager: Start Background Job

Confirm the start of the service processing by clicking "OK".
 


SAP Solution Manager: SAP Tutor Solution

Refresh the EWA report overview by clicking on "Refresh".
 



SAP Solution Manager: SAP Tutor Solution


After some time (several minutes), the service processing background job is finished, and the EWA report is displayed with a new status icon in the overview. In this case, the "green" OK sign means that the EWA report has been overall rated green. You might also receive a yellow (warning) or a red (alert) icon. The tiny mail / SAP icon means that this report has also been automatically sent to SAP. This happens either every four weeks (for each system) or if the report was rated red.
 



SAP Solution Manager: SAP Tutor Solution

Now you may access and view the EWA report. Click on "SAP Early Watch Alert" for the report you want to see.
 



SAP Solution Manager: Display report

Decide if the report should be displayed with or without graphics. For this tutorial, choose "EWA report with Graphics".




SAP Solution Manager
So here it is: the EWA report from system TCE.